subcontract LIV problem

Dear all:

When I try to do LIV (MIRO) for subcontract PO , system always show an error message

G/L account is not defined in chart of accounts LTPS

Message no. F5 507

Diagnosis

The general master data of the G/L account is not maintained in the

chart of accounts LTPS.

System Response

Error.

Procedure

Please correct your entry or create the master record.

But the message does not told me what G/L account I need .

Hope someone can tell me how to solve the problem.

Thanks .

(Our SAP version is 46C)

Dear all:When I try to do LIV (MIRO) for subcontract PO , system always show an error message G/L account is not defined in chart of accounts LTPS Message no. F5 507 Diagnosis The general master data of the G/L account is not maintained in the chart of accounts LTPS. System Response Error. Procedure Please correct your entry or create the master record. But the message does not told me what G/L account I need .Hope someone can tell me how to solve the problem.Thanks .(Our SAP version is 46C)

subcontract LIV problem

Very Helpfull

User Rating: Be the first one !
Train Asked on February 11, 2017 in logistics mm.
Add Comment
1 Answer(s)

System checks the Reconcilation Account of Vendor..

There is a problem with that Vendor ..

Create a Sub-contract PO for another Vendor & do MIGO and MIRO..

You will not have any issue..