MRP calculations

    Hi guys.

    I have problem with MRP planning.

    Example:

    1. The quantity of the material X on the stock is zero.

    2. I created one reservation for 5 pieces of the material X for 10.10.2007

    3. I run planning. Purchace requirement for 02.10.2007 is created for 5 pcs.

    For this moment I have planned 5 pcs of material X. The stock is still 0.

    4. I create reservation for 4 pcs. for tomorrow.

    5. MRP do not plan anything and I do not know why!?

    Pls help me./ Points will be rewarded

    Regards

    Piotrek

    Hi guys.I have problem with MRP planning. Example:1. The quantity of the material X on the stock is zero.2. I created one reservation for 5 pieces of the material X for 10.10.20073. I run planning. Purchace requirement for 02.10.2007 is created for 5 pcs.For this moment I have planned 5 pcs of material X. The stock is still 0.4. I create reservation for 4 pcs. for tomorrow.5. MRP do not plan anything and I do not know why!?Pls help me./ Points will be rewardedRegardsPiotrek

    MRP calculations

    Very Helpfull

    User Rating: Be the first one !
    Vice Professor Asked on March 3, 2017 in logistics mm.
    Add Comment
    1 Answer(s)

      Please check the date of reservation and planning date..

      Add Comment