Consingment issue

Hi,

I have created consignment info record price for X material from 15/5/2007 to 16/05/2007 is Rs 10

Iam doing GR ( between these dates) for qty is 100 @ Rs 10 and do the GI 50 Nos and taken the rate is Rs 10

Then i changed the Price Rs 16 Validy date is 16/05/2007 to 31/12/9999

after that i received GR 100 Nos For Rs 16.. Now the total qty is 150..

Now iam doing GI 150 nos and price taken is Rs 16.. My client is asking why the price taken Rs 16 for all GI quantities

Sytem should take the price Rs 10 for the 50 Nos and Rs 16 for 100 nos

How i can do this settings.. Pl advice

Regards,

Vijay

Hi,I have created consignment info record price for X material from 15/5/2007 to 16/05/2007 is Rs 10Iam doing GR ( between these dates) for qty is 100 @ Rs 10 and do the GI 50 Nos and taken the rate is Rs 10Then i changed the Price Rs 16 Validy date is 16/05/2007 to 31/12/9999after that i received GR 100 Nos For Rs 16.. Now the total qty is 150..Now iam doing GI 150 nos and price taken is Rs 16.. My client is asking why the price taken Rs 16 for all GI quantitiesSytem should take the price Rs…

Consingment issue

Very Helpfull

User Rating: Be the first one !
Supporter Asked on February 20, 2017 in logistics mm.
Add Comment
1 Answer(s)

Dear Vijay,

 

Consignment liability will create based on Goods issue / withdrawal date with reference Info record validity date. Not based on Goods Receipts.

 

Hope this info will be useful.

 

Bye,

 

Muralidhara

Add Comment

Your Answer

By posting your answer, you agree to the privacy policy and terms of service.