RE: Problem in migration projects. ByD

      Hi experts!

      Actually I am having a little problem with my task “Migration projects”. I am testing the migration tools for projects, and I can’t do it…

      I try migrate one project, but always show me the same error: “Milestone status not permitted; task PROJECT-1 is not marked as milestone”. But I dont add any task actually, I only want to migrate a simple project…


      Please anyone could help me?


      Thanks in advance for your support and regards

      Dear Alvoro,   Kindly execute the migration step by step, in the second step Convert values choose the "Edit Value Conversion for Milestone Status" and double click. Now change the value MIslestone status 2 to 3 and Confirm Values, Save and Close.   Then Execute the Simulation Import Steps.   If the issue is resolved then mark the thread as answered, if not then raise an incident.   Best regards, Sahalya

      User Rating: Be the first one !
      CMS Vice Professor Asked on November 2, 2016 in business bydesign.
      Add Comment
      1 Answers

        Dear Alvoro,

         

        Kindly execute the migration step by step, in the second step Convert values choose the “Edit Value Conversion for Milestone Status” and double click.

        Now change the value MIslestone status 2 to 3 and Confirm Values, Save and Close.

         

        Then Execute the Simulation Import Steps.

         

        If the issue is resolved then mark the thread as answered, if not then raise an incident.

         

        Best regards, Sahalya